Rhapsody of the Seas
receives a new motor, Cascade gets the tough job done two days ahead
of schedule
Cascade General Shipyard
in Portland has succesfully completed a complex main propulsion
motor replacement job. The work on the five-month-old diesel-electric
cruise ship Rhapsody of the Seas cured a problem which had plagued
the ship since it left the builder's yard.
On April 22, just 25
miles into its delivery voyage from the Chantiers de I'Atlantic
shipyard in St. Nazaire, France, the starboard propulsion motor
of the brand new 917-foot cruise ship overheated. The ship immediately
turned around and returned to St. Nazaire.
Rich Steck, manager,
public relations for Royal Caribbean International, said that on
inspection it was found some of the coils on the motor had burned
out. The ship spent a week in St. Nazaire while engineers and technicians
shunted past the burned out coils and re-tested the motor. With
slightly reduced power, the ship sailed again for New York. On the
crossing, however, the motor experienced more problems. More work
was done at New York which reduced output on the starboard motor
to 50 percent of power.
Workers at Cascade General
work carefully to
place the 43-ton, 8.5-megawatt replacement motor
through a 25-foot by 30-foot hole cut into the side
of the Rhapsody of the Seas' hull. Once inside,
it was skidded into position.
|
Time was now critical
as the ship was urgently needed for a sold-out cruise season in
Alaska. While the reduced power dropped the ship's speed a few knots,
the ship was still able to maintain its schedule. After a pair of
two-day promotional cruises the Rhapsody of the Seas departed to
Miami for more promotional work, then began its regular commercial
service on time with a Panama Canal positioning cruise May 19.
Upon arrival on the
West Coast, the ship immediately commenced its summer Alaska cruise
season, carrying more than 2,000 passengers each week.
However, by August,
the balky motor again began to act up. More technicians boarded
the ship and the vessel sailed one voyage with reduced speed on
a shortened itinerary while additional patch-up work was done.
The repairs were successful
but it was equally obvious a permanent solution was required.
A giant Anatov AN-124
cargo jet took off from France for Portland with the 43-ton replacement
motor while plans were made to complete the Alaska season. RCI then
canceled two Hawaiian cruises in September to free up three weeks
of time for the tricky motor replacement job.
On Sept. 15, the 78,000-gross-ton
Rhapsody of the Seas arrived alongside Cascade General's Swan Island
yard. For the shipyard, it was a brief bonanza. The equally large
two-year-old cruise ship Sun Princess had already been booked into
the drydock for its first guarantee drydocking and arrived an hour
and a half earlier. As the Rhapsody of the Seas tied up, the Sun
Princess was already entering the drydock for a nine-day stay.
For the next week, workers
began preparatory work dismantling the electric motor. When this
work was completed, and with the Sun Princess back in the water,
the Rhapsody of the Seas entered the drydock and was lifted out
of the water.
Surendra Menon, executive
vice-president, production at Cascade General, said "a 25-foot by
20-foot hole was cut in the side of the hull and a transformer had
to be removed." Then, using hydraulic jacks the damaged motor was
skidded out through the side of the ship. The 43-ton, 8.5-megawatt
replacement motor was then skidded into position. According to Menon,
there was "zero tolerance and zero clearance." A major limiting
factor was a switchboard converter room directly above the motor.
This not only limited the height available to work, but also precluded
cutting or heat in that area.
Menon beamed, "The work
was completed two days ahead of schedule."
The replacement motor
had been readily available as it had originally been ordered for
a RCI sistership now under construction.
Menon said the new motor
performed "beautifully" on sea trials and that "when she left the
drydock nothing would stop her."
All work performed by
Cascade General was warranty work for the builder's yard and the
motor manufacturer, CEGELEC.
RCI's Steck stressed
the motor problem was highly unusual. He pointed out that diesel-electric
propulsion and electric motors are common features of cruise ships
and have proved to be highly reliable. On Oct. 5, the ship resumed
its regular schedule, embarking a full complement of passengers
in San Diego for a Panama Canal cruise.
|