|
To say that Regal Princess
had a major facelift during its scheduled drydock period at Cascade
General Shipyard in Portland, Oregon, September 20 to October 4,
is something of an understatement.
In addition to the normal
drydock maintenance, three major changes were made to the Regal
Princess, explained Paul Barrett, superintendent engineer for Princess
Cruises. The vessel's Lido Cafe was extended and enclosed with an
aluminum structure. A youth center was installed above the Lido
Cafe and the atrium was completely remodeled.
"We did it to bring
the ship into the new millennium," said Barrett, who was project
manager for the atrium remodeling.
The Regal Princess was
built in 1991. Its sister ship, Crown Princess, will have a similar
retrofit next year and get an additional stern thruster.
Around the Clock
Work on Regal Princess'
deck extension commenced one month before the vessel arrived in
Portland. During the drydock at Cascade General, 240 craftsmen from
seven different companies worked 14-hour days; an additional 40
workers toiled throughout the night.
The huge scope of the
projects required the work of several contracting companies. Princess
Cruises selected Callenberg Engineering to do the electrical work,
while J.P. Colie expanded and refurbished the cafe on the Lido Deck
and added a children's center to the deck above. ELX Marine built
all the food service areas involved with the Lido Cafe conversion.
Maritime Services Corporation was contracted to remodel the atrium.
Before Regal Princess
set sail for Portland, contractors boarded the ship in Vancouver
and removed existing materials that were no longer required, such
as electrical installations, windows and revolving doors.
"As soon as the vessel
arrived in Portland, we had the Lido Deck extension in place in
24 hours and the children's center in place in 48 hours," said Surendra
Menon, executive vice president of Cascade General Portland Shipyard.
The installation time in the shipyard was only 11 days, Menon said.
"Three hundred and fifty people were employed from the shipyard.
Work took place 24 hours a day."
Lido Cafe
Bob Maddison was Princess
Cruises' project manager for the Lido Cafe extension and installation
of the youth center. James P. Colie & Associates worked for several
months on planning, purchasing and prefabrication prior to the drydock
installation.
The goal in refurbishing
the Lido Cafe was to make it a 24-hour restaurant with increased
seating capacity. "It was much more than redecorating an existing
space," said James P. Colie, the company's president. Workers removed
the entire interior of the cafe and expanded its dimensions outward
over the aft section of the Lido Deck and enclosed the addition
with windows.
A new glass wall was
installed at the perimeter of the new extension, which enclosed
an evening dining area, a dance floor and stage. A new decorative
ceiling encloses all the new ventilation trunking, as well as a
sprinkler system.
The rest of the existing
Lido Cafe was remodeled with new banquet seating arrangement, column
covers, decorative tile bulkheads, tiled floor, new beverage and
waiter stations, and a new-look serving line.
ELX Marine Division
contracted with Princess Cruises to build all the food-service areas
involved with the Lido Cafe conversion. "The design for the Regal
was modified to include the addition of a mini-galley and a repositioned
grill counter," explained Michael Chapman, project manager for ELX.
The Lido Cafe - before (insert)
and after (main picture)
|
For the new mini-galley,
ELX fitted in therma-module cooking equipment that is designed to
be hung off the wall. It takes about 10 percent less space than
conventional stand-alone equipment, Chapman said.
For the area to work
as a bistro in the evening, the new galley was installed within
the existing pantry area. This required its own ventilation, fire
insulation and fire-suppression equipment, as well as all the cooking
equipment usually found in a modern galley. A new pantry was created
as a food-preparation area.
At the forward end of
the new Lido Cafe, two new serving lines were installed on the open
deck. On the port side, a new salad bar was constructed with refrigeration
equipment and its own pantry and beverage station. On the starboard
side, a new hamburger bar was installed, again with its own pantry
and beverage station, as well as extraction and fire-suppression
equipment.
There are four new entrances
at the four corners of the new cafe, each with double swinging automatic
doors. Lighting was changed throughout. A new dimming system was
installed, new fire detectors, new PA system speakers, new theater
lighting over the dance floor and above the stage, as well as amplification
and sound equipment on the stage. All new and existing ceilings
were repainted, new granite bases were installed on all vertical
surfaces and the untiled floor areas were carpeted.
Children's Center
The children's center
is an entirely new addition to the Regal Princess, replacing a basketball
court. It was constructed at the shipyard prior to the drydock and
outfitted with insulation, ventilation trunking, sprinkler system
and cabling. As this was to be installed partially over the new
Lido deck extension, it could not be brought onto the ship until
the Lido extension was in place and consolidated.
The 2,000-square-foot
children's center contains four store rooms and two bathrooms. A
built-in, multi-purpose section can be used as a computer area or
an art workshop. The center can be divided into two rooms so that
younger children can be apart from teen-agers; it can also be used
for other purposes, such as conferences or meetings.
The atrium - before
|
The atrium - after
|
Atrium
The Regal Princess'
new atrium was modeled after the style adopted for the Sun Princess
and the Dawn Princess, said Barrett. It cost approximately $2 million
and it took 12 days. The project involved gutting the atrium area,
all three decks and one gift shop.
"The decor in the atrium
was eight years out of date," Barrett said. "There were a lot of
pink laminates with stainless steel and it wasn't particularly warm.
We recovered the wall laminates with a wood effect called Belbian
throughout the atrium." Marble toe kicks and wood crown moldings
make the whole area "warmer," he said. All pillars were clad with
marble and Belbian to "make them look more substantial," he added.
"We installed a decorative
marble floor at the base of the central staircase on deck five.
We placed marble planters (boxes for palm trees and flowers) at
the base of the existing columns," Barrett said. Bronze sculptures
adorn a lower-level pool.
A metallic sculpture
of dolphins is now the backdrop to the reception desk on starboard.
The face of the reception desk contains marble and wood moldings.
Maritime Services Corporation
(MSC) was responsible for the construction, fabrication and installation
of the atrium. "The project was very large in scope," said David
Culpepper, project manager for the company. "There were 15 separate
work items aboard the vessel that had to be completed. We had to
figure out how to fit so many people in such a limited space and
get all the work done in a limited amount of time." At one point,
workers had to install a chandelier 30 feet up.
"We remodeled the Bacchus
Bar, put up new signage and moldings on two storefronts, installed
20 marble planters on all three decks, installed a lace curtain
waterfall, two ponds and waterfalls, painted overheads, reconfigured
soffits, added wood trims to all the soffits, installed Formglas
decorative moldings, modified offices, shops, installed new column
wraps and recovered every wall in the atrium with Belbian."
Added Wren Swan, an
engineer for MSC, "The atrium was a very plain, simple space and
we put tons of marble into it. It looks very classy now."
The storefronts of decks
six and seven now contain marble, Formglas and wood moldings, as
well as brass-lettered shop signs. The Signature Collection shop,
which sells sundries, was completely stripped and remolded, with
new lighting, carpets, displays and wall panels.
On deck five La Patisserie
Bar now has three new rectangular ship-side windows that provide
natural lighting. Its bar face and soffits were upgraded with marble,
leather and wood moldings.
"We're very pleased
with the outcome," Barrett said. "It makes a substantial difference
to the look of the atrium. When you go back on the Crown Princess,
which has not been done yet, you really notice the difference. We
look forward to doing the Crown next year."
|