|
Cascade General lived
up to its reputation as the leading shipyard for cruise ship work
with the emergency replacement of a faulty generator on P&O's Sea
Princess. The 857' ship, built by Fincantieri in 1998, was in dry
dock at the Portland Shipyard for just nine days in September before
continuing south to San Francisco to embark passengers for a cruise
to Florida.
This challenging project
demanded a high level of coordination and cooperation from numerous
shipyard specialists. The effort began on the exterior with the
rigging crew building a 20' loading platform on the drydock floor.
At the same time, work proceeded inside the engine room to clear
an exit path for the 47-ton (GEC Alstom) generator. One welding
team was opening a 15' X 15' access in the side shell while another
was cutting a similar opening in the aft engine room bulkhead.
Two of the ship's four
propulsion transformers, each weighing 20 tons, were disconnected
and moved aside, catwalks lifted, and all wiring and piping blocking
the exit route labeled and cut. The generator was fitted with a
temporary shaft-support bracket, jacked up and rolled aft on a pair
of girders set up as temporary rails. It was then lifted and turned
onto a second set of rails running abeam, skidded out of the ship
and transported by drydock crane and trailer to an assembly bay.
With only 6mm of clearance
between the generators 20-ton rotor and 27-ton stator, they were
carefully separated using an overhead crane and a high-capacity
tri-lifter. The rotor was immediately inserted into a new stator
housing under the supervision of the manufacturers' representatives.
The re-built 14040 kVA, 6,600volt unit was returned to the ship
in less than 24 hours.
By the fifth day, the
generator was back in the engine room, allowing the bulkhead to
be closed up. The 2,100 volt transformers were then skidded into
position and secured to their bases. Once these three components
were safely back inside the hull, the final part of the puzzle,
the hull insert, was welded into place, ultrasonically tested, inspected
and approved by RINA.
Work to re-assemble the
engine room continued around the clock for the next four days, utilizing
the diverse abilities of Cascade General's engineering/technical
staff. Much of the progress depended on the experience and skill
of the company's tradesmen, but the task of shaft alignment has
been re-defined by the recent development of laser-sighting devices
that offer incredible accuracy when used properly. The Sea Princess'
generator and one of the four V-16 Sulzer engines were aligned to
1/10,000" (the thickness of a human hair) using the computerized
Fixturlaser system, which reduces stress on the bearings to the
absolute minimum.
During the drydocking,
Cascade General also overhauled the bow thrusters, sea valves, seachests
and strainers, prepared and coated the underwater and surface areas
and the topside white. The rudder and propeller shafts were inspected,
ballast tanks surveyed, all 16 lifeboats serviced and the davits
re-certified. Three fiberglass swimming-pool expansion tanks were
also replaced and the ship's waste-heat steam system repaired.
After 35 years at sea,
Captain David Christie was making his first visit to the Portland
Shipyard/Cascade General. "Other P&O captains had told me I'd be
impressed by the service here, but I still wasn't prepared for such
a very pleasant experience," he observed. "This is a great yard,
as good if not better than anywhere else I've been. They are very
aware of the needs of cruise ship operations and have some extraordinary
people on their management team, " he continued. "The yard itself
is clean, the people efficient, and they never say no to a request.
It's been a great success."
The Sea Princess departed
the Portland Shipyard after nine days with the repaired generator
completely installed. Minor finish work continued en route to San
Francisco, where the fourth engine was re-started, on schedule,
and full power restored. "This is the second cruise ship in three
years to experience this type of electrical problem (on the West
Coast)," observed Cascade General executive vice-president Suren
Menon. "Both of them were repaired here in Portland. I think that
record speaks for itself. " Immediately following the Sea Princess,
the Nieu Amsterdam arrived at the Portland Shipyard for a complete
refit and re-flagging for service in the Hawaiian Islands for its
new owner, United States Lines, a subsidiary of American Classic
Voyages Co.
|
|
|
Related articles
Cascade
General Completes River Boat Conversion In Five Months
Top
To Bottom Overhaul For The Crystal Harmony
|
|
Cascade General operates Portland Shipyard,
the largest and most complete ship repair and industrial facility on the West
Coast of the United States. We provide full-service repairs and conversions for
tankers, cruise ships, bulk carriers, container ships, government vessels, tugs,
barges and workboats. Cascade General's Portland facility includes a 60-acre (24.2
ha) yard, 550,000 square feet (51,096 square meters) of craft shops, more than
7,600 ft. (2,326 meters) of full-service repair berths, and two floating dry docks.
|