|
The July 1999 announcement
that Cascade General had won the contract to build a 124 MW power
barge for delivery to Guatemala in just nine months surprised many
observers and focused national attention on the Portland, Oregon
company. Under its management, the Portland Shipyard has carved
out a reputation as a leading American provider of ship repair and
conversion services. Its core business has been the Alaskan tanker
trade year round, plus cruise ship overhauls.
Although no new construction
had been undertaken there since the 1980s, Cascade General intended
to leap back into the newbuilding business with the largest, most
advanced vessel of its kind in the world. On a 279' X 104' hull,
this floating power station would house seven MAN B&W 25,000 hp
diesel generators, each weighing 330 tons, and capable of generating
enough electricity to supply 60,000 US homes. This clearly represented
a challenge as well as an opportunity for the company, and particularly
for executive vice president Suren Menon, the man most responsible
for the company's success in the cruise ship sector.
Menon had no doubts that
he could deliver a top-class product on time. "We'd clearly proved
that the Portland Shipyard could prefabricate and handle large modules,
like deck extensions and thruster tunnels and double bottom additions
to hulls. Menon feels that trouble-shooting conversion projects
is in many ways more demanding than a properly planned new-building
program. So the chance to start from a clean sheet was something
the entire management team at the Portland Shipyard was anticipating.
Cascade General had the
skills, the manpower, and the facility. The barge design, by Kvaerner
Masa Marine of Vancouver, Canada, gave them the chance to make the
maximum use of recent advances in modular building methods. "The
physical layout of the yard, our extensive covered working spaces,
and the technical expertise we've developed are all well suited
to modular assembly," Menon stressed. "This project represented
the best opportunity for us to re-enter the new construction field."
The first steel was cut
on June 15, and work was soon under way on numerous modules in separate
work areas. First to be completed were the machinery packages carrying
all the auxiliary equipment involved in fuel storage and delivery.
Everything, including pumps, filters, purifiers and pre-heaters,
was pre-assembled on shore and lowered into the barge hull through
deck openings. By October, the deck was closed up and ready for
the installation of engine skids.
The high capacity cooling
system for the power plant consisted of seven 18" cooling water
inlets and pumps in the stern. Rather than manhandle and fit these
below decks, the barge was launched minus its stern. The aft compartment,
designated the "integrated cooling module," was constructed separately
with all its machinery pre-fitted, and welded permanently into place.
In November, the deckhouse, an impressive 90' long, three-stories
high and weighing 295 tons, was rolled out of its building bay on
a multi-wheeled trailer and moved 100 meters to the dockside. From
there it was lowered into place onto the barge stern by a heavy-lift
floating crane.
When five of the engines
arrived in early December, the shipyard's diverse resources again
proved their value. Cascade General's dock crews routinely drydock
the largest ships on the west coast. The heavy-lift transport ship
was moored alongside the power barge in a sheltered location between
two of the yard's dry docks. Over a 48-hour period, the MAN B&W
engines, encased in plywood, emerged from the depths of the ship's
hold and were gently lowered onto a pair of girders spanning the
length of the barge deck.
They were followed by
five generators, each weighing in at 65 tons. (The last two engines
were shipped separately in January.) Once the barge was returned
to the dockside, riggers skidded these huge power plants into position
using old-fashioned grease on the skids. The machinist teams moved
in to attach the motor mounts and make final adjustments. Finally,
the engines were set in final position. The 13.8Kv Siemens generators
were then positioned by a dockside crane, aligned by laser, and
connected to the engine's output shaft.
From the start, wiring
and plumbing teams had been pre-outfitting as much of the final
seven miles of piping and thirty-five miles of wiring as possible.
Banks of wire runs were in place on and below the main deck well
before the engines arrived, and all cooling and fuel systems were
established and ready for connection. The next step in this carefully-choreographed
performance was the placement of the seven engine-service modules.
These 40-ton units consolidate
all oil, fuel and coolant, pumping and filtering systems into a
machinery tower 30' high and 25' wide. They were built on a production
line, mounted on rollers, and moved out of the workshop, across
the yard and within reach of the dockside cranes. With all seven
units in place, the far side of the engine hall became a solid wall
of machinery. This concept markedly reduces the usual engine room
clutter and improves access to the engines themselves.
With all the separate
elements in place on the main deck, the 50' high engine hall was
lifted and lowered into position over the generators in three sections.
These were united and work then began overhead to install a moving
gantry system, cooling fans for the generators, and the exhaust
pipes. These oversized stainless tubes are connected to the exhaust
stacks, which rise an impressive 131' (40 m) above the waterline,
supported by a steel framework. Testing of the individual generators
began on schedule in February.
"We are fortunate enough
to have a 230 Kv powerline and a sub-station serving the shipyard.
This permits us to connect each engine to the power grid and run
it at full capacity," Menon noted. "We were able to test each engine,
correct any voltage fluctuations, and verify the entire system,"
he added. This ability to perform acceptance testing on-site saved
the Esperanza's operators at least a month of trials in Guatemala.
Mechanical completion was achieved on April 10, 2000, a total contract
period of less than 11 months. The Esperanza was floated onboard
a Dock Wise submersible ship on April 15 and arrived in Guatemala
two weeks later.
To provide the best possible
service in this tropical environment, the barge is protected throughout
by a 15-year paint system. The control room is air conditioned and
engine operations are fully computerized. Every engine parameter,
including temperatures and pressures at numerous locations, is monitored
via touch screens in the air-conditioned control room. The emissions
will be regularly analyzed by instruments in the exhaust stacks
to ensure compliance with environmental standards set by the World
Bank. The Esperanza's owner is Puerto Quetzal Power Limited, a joint
venture between Enron, one of the world's leading power providers
and Centrans Energy Services, a consortium of Guatemalan and foreign
investors.
Terri Deskins, director
of sales and business development for Cascade General, sees great
potential for the yard to leverage its success with the power barge
into a wide range of modular construction--from floating industrial
plants to ships in the 300-400' range. She points out that Portland
is where modern shipbuilding really began, in 1942, when Henry Kaiser
started turning out Liberty ships for the war effort the same way
Henry Ford built cars. "It's a proud tradition," Deskins said, "and
we intend to make new construction the rule, not the exception,
once again in the new Portland Shipyard."
|
|
|
Related
articles
Cascade
General to Build 124 MW Power Barge for Germany-Based MAN B&W
Engines
for Floating Power Station Arrive at Cascade General
Cascade
General Busy "On All Fronts"
124MW
Power Barge Constructed by Cascade General Enroute to Guatemala
|