|
Cascade General began
2000 with an intensive five-month conversion project to deliver
the 218Õ (66m) luxury riverboat Columbia Queen to the Delta Queen
Steamboat Company by May 24. The vessel arrived at the Portland
Shipyard as a bare shell at the end of December, and within days,
shipyard crews were working simultaneously on all five decks. New
stairways and walls were fitted and hundreds of windows cut on the
four passenger decks. At the same time, all the utilities were installed
overhead on racks in the ceiling void. These included not just the
normal shipboard amenities, but also satellite TV, ship-to-shore
telephones and data lines to all 105 cabins.
The Columbia Queen was
originally built in 1994 for use as a casino with two 700 HP Cummins
engines for electrical generation and two 950 HP Cummins for slow-speed
propulsion. For its new role as an inland cruise ship, a complete
re-configuration of the drive system was specified by naval architects
Rodney Lay & Associates of Jacksonville, Fl. They called for a huge
increase of propulsion power from 1900 HP to 4600 HP, to enable
the ship to maneuver through the eight locks of the Columbia and
Snake rivers in high winds and provide a cruising speed of twelve
knots.
Cascade General's mechanical
team began this challenging re-power by opening four access panels
in the main deck, and building a new machinery space in the stern
compartment. The existing 950 HP mains were then hoisted out of
the engine room, and lowered into the stern where they became the
auxiliaries, connected to upward-angled shafts turning azimuthing
sternthrusters.
The new mains were to
be a pair of 1350 HP Cummins. They were moved by dockside crane
to the main deck level, skidded through a doorway by the rigging
crew, then lowered into the two vacated spaces in the main engine
room. In the Portland Shipyard's Dry Dock 1, they were connected
to conventional shafts turning 58" diameter four-bladed propellers
in tunnels. The 950 HP auxiliaries were mated to Schottel azimuthing
drives with fore and aft propellers, fitted in new transom wells.
All external work, including
bottom painting and the insertion of the passenger elevator, was
also completed in the dry dock while preliminary work was completed
on the interior.
With the infrastructure
in place to support all the demands of modern river travel, the
effort began to create 105 traditional-style cabins, three lounges
and the central dining room. All the interior structures, including
the superbly equipped galley and dining hall were completed and
ready for finish work by April. The ship's dˇcor and all furnishings
have been carefully selected to create the atmosphere of a 19th
century riverboat.
In trials, the ship achieved
a speed of 12 knots with all four engines, and was able to cruise
under mains only at 10.5 knots. The combination of azimuthing drives
and the 350 HP bowthruster produces a high degree of maneuverability.
Fully equipped wing steering stations give the captain complete
control during docking,
Safety features include
the Swedish Nittan fire-prevention system, automatic fire doors,
and extremely fire-resistant stair towers, a rear-looking remote
TV camera, and main deck speakers with "talk back" microphones.
The ship passed its Coast Guard trials on May 22 with flying colors.
Cruise Ship Overhauls
Cascade General drydocked
two cruise ships in the Portland Shipyard this spring. The first
was Holland America Line's Statendam in April for a six-day stay.
The 720Õ (220 m) ship went straight onto Drydock 4, where the rudder,
propeller and shaft were staged and prepared for inspection by a
LloydÕs surveyor. The propellers were polished and the port shaft
seal was replaced.
Work on the bottom continued
with cleaning and inspection of 22 sea-valves and replacement of
anodes. The stabilizers and thruster tunnels were also opened for
ownerÕs inspection, while the hull below the waterline was blasted
and re-painted with an International four-coat system.
The shell plating was
repaired in three locations and a cracked bulkhead in the forward
ballast deep tank was repaired. All welds were inspected and approved
by Lloyds. Work in the shipÕs interior ranged from the renewal of
piping in the deck drains to the replacement of the charge-air cooling
units on three of the shipÕs five GMT Sulzer diesel engines.
Also in the engine room,
a Cascade General crew installed the foundations for two 4,000 gallon
wastewater treatment tanks and a pump module for a state-of-the-art
blackwater treatment system. This equipment, produced in Canada
by Zenon, also required the routing of 200Õ of 6" and 8" aeration
piping through two double-bottom blackwater tanks. (The Statendam
is the first Holland America ship to use this method, which exceeds
new standards for overboard discharge.)
On the boat deck, twelve
lifeboat davits were completely dis-assembled for a five-year inspection.
The traveling beams and track wheels were removed and inspected,
hydraulic operating systems were overhauled, and sheaves and pins
replaced according to the manufacturerÕs specifications. Finally,
the re-assembled units were weight tested to 22 metric tonnes and
re-certified.
The 790'(240m) Crystal
Harmony arrived at Cascade General in May for a ten-day stopover.
The overhaul on this ten-year old ship included an overhaul of the
hull below the waterline, extensive interior remodeling and steel
replacement in the pool areas on Deck 11. The work actually began
on the ship in Los Angeles, where Cascade General sent a mobile
crew to join the ship.
The primary task was
an overhaul of one of the auxiliary boilers. A second team embarked
in San Francisco to clean ballast tanks prior to structural repairs
and tank preservation work. "We depend on our advance teams to clear
the way for the shipyard phase," explained Cascade General Executive
Vice President and cruise ship specialist Suren Menon. "The more
they can accomplish while the ship is at sea, the more effectively
we can use the limited time in the shipyard."
On the ship's Lido Deck,
the Neptune and Seahorse pools needed new surrounds, and new steel
foundations were required under the two Jacuzzis. While the Crystal
Harmony was still in New Orleans, a complete advance survey was
made of the pool areas, and measurements taken to enable new surrounds
to be pre-fabricated in Portland. The project resumed one month
later in Canadian waters, after the passengers had disembarked,
when a third crew arrived to begin removing the steelwork from all
four pools.
Once the ship was high
and dry on Portland Shipyard's 982'(299m) Dry Dock 4, work began
on all the mechanical systems below the waterline which were also
due for 10-year inspection. The Sperry stabilizer fins, weighing
27 tons each, were removed to a building bay where they were completely
refurbished; both the 1000 Kw Lips bowthrusters were extracted for
complete dis-assembly, overhaul and testing in one of the shipyard
machine shops.
Multiple paint layers
were blasted away to clean the entire hull down to bare metal and
a five-coat Jotun paint system applied. Welding crews began replacing
corroded steel in several locations. To comply with Lloyd's rules,
over fifty sea valves were overhauled and inspections carried out
on propellers, shafting and rudders.
"It's a pleasure for
me to see a ten-year old ship that's this well maintained," Menon
added. "We've done our part to make sure she maintains her six-star
rating and is ready for many more years of service."
Paul Buck Gets SOLAS
Upgrade
The 32,572-ton deadweight
product carrier Paul Buck was in the Portland Shipyard in June for
a drydocking, mechanical overhaul, and the addition of a raised,
centerline walkway extending 400'from the house to the foredeck.
This addition meets the 1998 SOLAS requirement for all oil tankers
to have "safe access to the bow" by 2001. The Paul Buck is designated
a T-5 Replacement and operates under a long-term charter to the
Military Sealift Command to carry refined petroleum products.
Prior to the 615'(185m)
ship's arrival, Cascade General prefabricated the structure in 15-20'(5-6m) sections, which were prepared and painted onshore and lifted
into place during while the ship was on the 982'(299m) Dry Dock
4. Situated 8'above the deck, the walkway incorporates two existing
refueling-at-sea platforms and includes seven firefighting monitors
that were formerly at deck level. The decking is Fiber Grate non-skid.
The original fifteen-year
old re-fueling platforms were stripped of all fittings and hydroblasted
at 40,000 psi before re-coating. This method was also successfully
used on the foredeck, windlass, bulwarks and rudder horn compartments.
This allowed maintenance work on the piping to the 21 separate tanks
to proceed without interruption.
On the dry dock floor,
the propeller was pulled to correct a seal leak, a rudder pintle
pulled and rebuilt, and the topsides above the waterline blasted
to bare metal and given a five-part coating. Eighty anodes were
removed and replaced. The ship's owners, Ocean Carrier, were also
using this opportunity to carry out some life-cycle extension work
in the double bottom, where an inspection had revealed the need
for preventative maintenance.
To restore the ship's
ballast tanks to top condition, a complete blast and coat of 180,000
sq. ft. of surface area was required. "They came to Portland specifically
because we were prepared to complete the internal blasting in the
time available," explained Cascade General project manager Dave
Byers. "We had a hundred-man crew working in the tanks from the
day the ship arrived," he added. "It's not an easy job down there,
with minimal headroom, but we were ready to start painting within
a week."
In the engine room, Cascade
General machinists completed a complete overhaul of the IHI Sulzer
5RTA76 low-speed engine. All five pistons, plus one spare, were
removed and trucked to a specialist shop in Long Beach CA. for refurbishing.
The 11,000 Kw unit was re-built with four new cross-head bearings
in a total of fifteen days. The turbo charger was removed for refurbishing
by ABB in Seattle, and the Caterpillar 3516 genset was also rebuilt.
New Frames for the
Sea Trident
Also in June, the 633'(190m) Greek bulk carrier Sea Trident made a three-week dockside
stop in the Portland Shipyard for the replacement of most of the
frames in the #1 and #5 holds. The deterioration, caused by corrosion,
was detected by an ABS inspector after the ship had discharged cargo
in Los Angeles. The ship's owners, Marine Managers Ltd of Piraeus,
Greece, selected Cascade General to make the necessary repairs,
and the ship detoured north to the Columbia River.
The project required
that three levels of staging be erected to give the ship fitters
safe access to the 50'-high sides of the hold. The old frames were
removed in an alternating pattern to maintain hull shape. The curved
frame shapes in the forward sections were lofted onto plywood templates
before removal to ensure an accurate fit.
Replacement frames were
cut from 5/8" plate and hoisted into place using temporary lifting
eyes welded to the side-deck beams. Many port and starboard structural
brackets were also replaced at the bulkheads, and covered with new
shed plates. Over 100,000 lbs of steel was replaced and inspected
by the ABS representative in Portland. Cascade General completed
the repairs on schedule in two weeks, using approximately 120 men
per day in three shifts.
AlaskanTanker Repair
Recognizing the increasing
demands on west coast tanker operators, Cascade General signed a
maintenance and repair alliance with Alaska Tanker Company (ATC),
the largest operator of US-flagged tankers on the west coast, with
eleven vessels under its banner. By mid-year, eight American-flagged
crude carriers had made stops in the Portland Shipyard for general
maintenance in the yard's 983'(299m) Dry Dock 4.
Cascade General also
continued to lead the industry on the west coast in the field of
mobile ship-repair. Since 1996, the mobile squads have become an
essential part of the company's service, providing a fast response
anywhere between the Gulf of Alaska and southern California. Mobile
crews made 34 tanker visits in the first half of the year.
Taking this concept a
stage further, Cascade General has established a voyage repair station
in Port Angeles, Washington. This location is strategically situated
on the route for ships supplying the refineries of Puget Sound.
Five tankers had been repaired at the dockside by mid-year.
In addition, over 60
voyage repair projects were completed on all manner of vessels transiting
the Columbia River, including tugs, barges and dredges. Response
teams have also been sent as far as Hawaii to work on the cruise
ship SS Independance and American Samoa on the Crowley tug American
Salvor.
"Our record this year
shows that we have made significant progress at the Portland Shipyard
in diversifying our business. We also handled two complex projects
simultaneously: the construction of a 124 MW Power Barge and the
cruise ship conversion," stated Frank Foti, CEO and President of
Cascade General.
From the start, wiring
and plumbing teams had been pre-outfitting as much of the final
seven miles of piping and thirty-five miles of wiring as possible.
Banks of wire runs were in place on and below the main deck well
before the engines arrived, and all cooling and fuel systems were
established and ready for connection. The next step in this carefully-choreographed
performance was the placement of the seven engine-service modules.
These 40-ton units consolidate
all oil, fuel and coolant, pumping and filtering systems into a
machinery tower 30'high and 25'wide. They were built on a production
line, mounted on rollers, and moved out of the workshop, across
the yard and within reach of the dockside cranes. With all seven
units in place, the far side of the engine hall became a solid wall
of machinery. This concept markedly reduces the usual engine room
clutter and improves access to the engines themselves.
With all the separate
elements in place on the main deck, the 50'high engine hall was
lifted and lowered into position over the generators in three sections.
These were united and work then began overhead to install a moving
gantry system, cooling fans for the generators, and the exhaust
pipes. These oversized stainless tubes are connected to the exhaust
stacks, which rise an impressive 131'(40 m) above the waterline,
supported by a steel framework. Testing of the individual generators
began on schedule in February.
"We are fortunate enough
to have a 230 Kv powerline and a sub-station serving the shipyard.
This permits us to connect each engine to the power grid and run
it at full capacity," Menon noted. "We were able to test each engine,
correct any voltage fluctuations, and verify the entire system,"
he added. This ability to perform acceptance testing on-site saved
the Esperanza's operators at least a month of trials in Guatemala.
Mechanical completion was achieved on April 10, 2000, a total contract
period of less than 11 months. The Esperanza was floated onboard
a Dock Wise submersible ship on April 15 and arrived in Guatemala
two weeks later.
To provide the best possible
service in this tropical environment, the barge is protected throughout
by a 15-year paint system. The control room is air conditioned and
engine operations are fully computerized. Every engine parameter,
including temperatures and pressures at numerous locations, is monitored
via touch screens in the air-conditioned control room. The emissions
will be regularly analyzed by instruments in the exhaust stacks
to ensure compliance with environmental standards set by the World
Bank. The Esperanza's owner is Puerto Quetzal Power Limited, a joint
venture between Enron, one of the world's leading power providers
and Centrans Energy Services, a consortium of Guatemalan and foreign
investors.
Terri Deskins, director
of sales and business development for Cascade General, sees great
potential for the yard to leverage its success with the power barge
into a wide range of modular construction--from floating industrial
plants to ships in the 300-400'range. She points out that Portland
is where modern shipbuilding really began, in 1942, when Henry Kaiser
started turning out Liberty ships for the war effort the same way
Henry Ford built cars. "It's a proud tradition," Deskins said, "and
we intend to make new construction the rule, not the exception,
once again in the new Portland Shipyard."
|