|
On a well-run cruise,
the passengers should be unaware of the intense, behind-the-scenes
effort that the crew makes to ensure a carefree vacation. The same
standard should apply when a cruise ship is in dry dock, says Suren
Menon, Executive Vice President and cruise ship specialist at Cascade
General. Only in this case, it's the crew and sub-contractors who
should be unaware of the effort the shipyard is putting out.
For Menon, the yard
is the Portland Shipyard, which has gained the majority of cruise
ship work on the US West Coast since Cascade General took over the
operation in 1995. In 1999, the yard successfully handled work on
two ships simultaneously in the spring and fall (autumn) and welcomed
a fifth arrival before year's end. The last visitor of the 1990s
was the 245m (811') Regal Princess, which Princess Lines had scheduled
for a Christmas departure from Los Angeles, followed by a special
millennial New Year's cruise.
The Regal Princess represents
a particular success for Menon and Cascade General, since it was
only a year ago that it was in the yard for a major facelift. At
that time, the yard installed a two-deck stern extension, to enlarge
the Lido Cafe and create a new children's center, and completely
remodeled the atrium. This time, the 1600-passenger ship was returning
for the installation of an additional stern thruster, dining room
remodeling and initial work for a new incinerator installation.
Just as the ship's managers
have been planning its year 2000 program for the past year, Menon
and his team have put countless hours into their planning process.
"We received the preliminary RFQ (request for quotation) over a
year ago," he said in late November during a brief interlude before
the ship's arrival. "I didn't feel I needed to do a preliminary
survey, since I was already very familiar with a sister ship. So
we went straight to work on the bid."
In March of this year,
the specifications and drawings were completed and sent to qualified
yards in San Diego, San Francisco and Vancouver BC. Menon flew to
Alaska to inspect the ship during the summer. The pressure intensified
as the Cascade General team reviewed their numbers. All the bids
were evaluated in September by Princess Cruises and the multi-million
dollar contract awarded.
"Once we learned our
bid was successful, we moved immediately into a second phase," Menon
continued. "I flew to Honolulu to introduce myself to the captain
and the chief engineer. Then, in Los Angeles I met with the company's
superintendent of repairs, Lars Nordin, the vice president of technical
operations, and their specialist designers and interior decorators."
Back in Oregon, Menon
assembled his team, consisting of day and night superintendents
and senior foremen, representing all the shipyard trades. They began
regular production meetings where every line item on the specification
was scrutinized and detailed. Besides the work which directly involves
the shipyard--the thruster installation and all drydock work--they
needed to plan how to meet the demands of the sixty specialist sub-contractors
for services like crane lifts, rigging, offices, housing and firewatching.
Because of the limited
time available, Menon considers it vital that some of his men begin
the hands-on work on a project like this before the ship arrives
in Portland. Consequently, two weeks before it was due, the first
mobile team was flown out to meet the ship in Acapulco, Mexico.
Their task was to access and clean the tanks and bilge area that
would comprise the new thruster compartment. A week later, the second
crew flew to Los Angeles. After the passengers had disembarked,
they began preparing the interior. "Our traveling teams save us
a week's work in the shipyard," Menon assured me.
Forty-eight hours before
the ship reached Portland, the new controllable-pitch Lipps stern
thruster had arrived by truck after shipment from Holland. Menon
and his foremen were busy checking to ensure all the sub-contractors
had their tools, materials and personnel on site. (If anyone isn't
absolutely ready to go, then it's up to the yard to find out who
and what is missing and locate replacements.) Many specialists are
based in Florida cities that are homeports for the cruise lines.
One exception is Maritime Services Corporation, which is based in
Hood River, 60 miles from Portland.
The Regal Princess picked
up a Columbia Bar pilot early in the morning of December 1st, and
entered the Columbia River. A river pilot took over off Astoria,
and the ship arrived in Portland at 9.15 PM. By then, a strong breeze
was whipping up from the south. Cascade General's dockmaster, Mark
Root, watched anxiously as the wind gauge on his control panel registered
gusts up to 30 mph. Four Foss tugs were stationed around the towering
Regal Princess, as her captain lined up his approach and began to
edge cautiously toward Dry Dock 4.
From the ends of the
982' long dry dock, the rigging crews watched intently as the tugs
churned the waters of the Willamette River, trying to hold the 35,000-ton
displacement ship in place. As the wind gusted higher, it became
clear that the maneuver was not possible. At 9.45PM the ship dropped
back, spun around in mid stream and came into a berth at the dockside.
The next morning, conditions were perfect and the ship was high
and dry in a couple of hours.
Approximately 350 journeymen
were ready to begin work, with an absolute time limit of 18 days
for completion. The drydock crew set to work, quickly positioning
an array of hoses, water and sand blasting tanks under the ship.
The bottom was given a "light blast" sufficient to remove loose
paint and expose any corroded areas. These were blasted again to
expose bare metal and then received the first of five coats of primer,
followed by anti-fouling.
The thruster installation
was part of a continuing upgrade of the entire Princess fleet to
enable safer docking in smaller, more remote ports. Cascade General
has previously added thrusters to the Sky Princess and Crown Princess
in 1997-98, while they were lifted on its 983' Dry Dock 4.
The hull was opened
and the computer-cut parts for the necessary, structural reinforcement
lifted into the compartment. The three frames filling the 2.8m (9')
wide space between two existing bulkheads were extended from 6.25"
(160mm) to 700mm (27.5"). 160mm face plates were added to these
webs and connected to three new overhead beams, distributing the
thruster's loads further into the structure.
This also provided a
strong point to hoist the thruster's 1515kw (2,000hp) Hyundai electric
motor up from the dry dock floor and safely suspend it until the
Lipps thruster, weighing 8,900kg (20,000lbs), could be hauled into
position. Once the thruster was permanently welded into the shell
and frames, the motor was lowered onto the drive shaft and the electric,
hydraulic and cooling systems connected. The exterior welds were
x-rayed and approved by RINA, the ship's classification society,
which also inspected all the system installations.
The new thruster takes
power from the ship's diesel-electric propulsion system, powered
by four MAN 8-cylinder diesels, which produce 36,800 Kw. The controllable
pitch of the new thruster will provide superior control, while the
more powerful motor will produce 50% more torque than the existing
stern thruster.
Higher in the ship,
on decks 6,7 and 8, work also proceeded on the foundations for a
Team Tec Golar waste incinerator, which included separate mixing
tanks, fan and ducts. All the plans necessary for all of these modifications
were prepared by Rosenblatt & Sons naval architects of San Francisco,
with whom the yard has established a good relationship over the
years.
Out on the dock, a boat
shop had been erected around the ship's four 14.7m (48') tenders
and fiberglass repair work was underway. By the second week, the
superintendent's final list of work orders totaled 114 separate
items, ranging from marking the anchor chain on the dock floor to
assisting the swimming pool re-tiling experts on the top deck.
With all the underwater
work completed, the ship was ready to come off the dry dock on the
evening of December 15th, but incredibly, the wind picked up during
the day and was howling by the afternoon. With gusts of 40 knots
making walking difficult, the operation was postponed until the
morning, when once again, calm conditions prevailed. Nonetheless,
all the shipyard's work was completed ahead of schedule. Except
for the unusual weather, the project had proceeded smoothly. As
planned, work would continue on the dining room while the ship sailed
south. Life on board had continued normally for the 700 crew, and
the Regal Princess would be on time for the millennium sailing!
|
|
|
Related
articles
Cascade
General on Schedule for Cruise Ships (July 28)
Cascade
General on Schedule for Cruise Ships (Sep. 22)
Cascade
General on Cruise Ship Schedule (Oct. 14)
|