|
While transiting the
Columbia River to unload deck cargo in Vancouver, Washington, the
568' Turkish bulk carrier, Cenk Kaptanoglu, lost power and collided
with the BHP dock in Kalama, Washington. The impact caused major
damage to the bow and left the ship wedged solidly into the dock.
It was pulled free by a tug and moored for inspection. The area
of impact extended from the starboard hawse pipe to the portside
of #1 hold and ran from the waterline to the forecastle deck. The
36,788 ton DWT vessel was given an exhaustive survey, a temporary
patch at the waterline, and towed to Vancouver.
After consultations between
the U.S. Coast Guard, the Kaptanoglu Shipping Group and the insurers,
the ship was moved to Portland Shipyard for repair by Cascade General.
In a sheltered berth between the yard's dry dock #1 and #3, three
work barges were rigged around the bow, and staging erected to permit
a complete, in-water repair. While preparatory work proceeded, Cascade
General's loft crew obtained the original design offsets used by
Hyundai to build the ship in 1982. These were input to a CAD program,
then converted to CNC files, allowing all the replacement steel
to be computer-cut and pre-fabricated.
The entire port bow above
the waterline and much of the starboard bow was cut away, leaving
only the starboard half of the forecastle deck intact. The warped
section of deck was released from the deck beams and straightened
using a combination of heavy girders, weights and hydraulic jacks.
With the cargo of mahogany curtained off in the #1 hold, the re-building
began with the replacement of damaged shell frames forward of the
#1 bulkhead. The port half of the forepeak tank bottom was replaced
and a new, prefabricated centerline bulkhead and port chainlocker
were moved into position.
The shape of the bow
was reconstructed on the port side with seventeen new frames, including
four web frames, plus five frames on the starboard side. The complete
framework for the stem was fabricated onshore and lifted into place,
followed by the new port half of the forepeak deck and the upper
portside frames. At the same time, a 20'-wide section of the #1
(collision) bulkhead was replaced and the parts for the port summer
ballast tank were lifted into position and assembled, permitting
the forward hold to be closed up. With the bow, web frames and some
temporary supports erected, the new forecastle deck was lowered
onto the ship.
Re-plating the hull
with 5/8" steel began at the waterline, then progressed up the overhanging
bow sections, matching the interior progress. Rolled 3/4" steel
wrapper panels were fitted at the stem, then X-ray testing was used
to check the quality of exterior welds and to meet the standards
for Lloyd's certification. The original bollards and both hawse
pipes were re-attached and a new bulwark fitted to complete the
deck work.
"This project required
165 tons of steel and a total re-build of the bow. Fortunately,
we were able to use our automated production systems to pre-fabricate
all the components for the new bow," explained Cascade General Executive
Vice President Andrew Rowe. "However the actual re-construction
with the ship afloat, was very much a hands-on job, which demanded
precise work in difficult conditions. That's when we rely on the
craftsmanship of our workforce at Portland Shipyard. We're all very
satisfied with the results."
|
|
|
Related
articles
Cascade
General Building International Flag Connection
Cascade
General Repairing Turkish Ship After Collision
|
|
Cascade General operates Portland Shipyard,
the largest and most complete ship repair and industrial facility on the West
Coast of the United States. We provide full-service repairs and conversions for
tankers, cruise ships, bulk carriers, container ships, government vessels, tugs,
barges and workboats. Cascade General's Portland facility includes a 60-acre (24.2
ha) yard, 550,000 square feet (51,096 square meters) of craft shops, more than
7,600 ft. (2,326 meters) of full-service repair berths, and two floating dry docks.
|