|
After twenty years in
lay-up/ready reserve, the Glomar Explorer is being revived as a
civilian ship.
With the decks stripped
of 25.5 million lbs (11.5 million kg) of superstructure, the 619-foot
(188.7 m) Glomar Explorer was lifted this February in Dry Dock 4
at the Portland Shipyard for a unique conversion project. Today
with oil wells being discovered at ever-greater depths, the Glomar
Explorer has found a new mission as a deep-water drill ship. It
has been chartered by its original builders, Global Marine Drilling
of Houston, TX. Cascade General, the company which took over sole
control of the Portland Shipyard in 1995, was selected to reconfigure
the vessel.
The contract, valued
in excess of $18 million, requires the addition of some 4,500,000
lbs (2,041,155 kg) of steel to fill the "moon pool", an
open area occupying the central third of the hull to create interior
machinery spaces. "The Glomar Explorer conversion is the largest,
most complex project in the history of this yard," said Cascade
General Executive Vice President Andrew Rowe. "It is enabling
us to demonstrate the full potential of the Portland Shipyard and
Cascade General as a major player in the US conversion market."
The primary challenge
was to replace the retractable, 200-foot (60.7 m) gates under the
moon pool with prefabricated double-bottom sections, leaving a 74-x
42-foot (22.5 x 12.8 m) drilling well. After making a thorough survey
in San Francisco, Cascade General's production engineering staff
established a tight schedule to complete the work by July 1997.
Design and pre-fabrication began immediately.
When the ship arrived
in Portland, it was lifted in the 982-foot (299.3 m) Dry Dock 4
and blocked at the bilges with a 12-foot (3.7 m) clearance. In a
carefully orchestrated sequence, the gate fittings were cut away,
the gates lowered and the dock partially submerged. In a delicate
operation using winches then tugs, the moon pool gates were hauled
free between the bilge blocks.
The new double-bottom
modules were then moved by barge onto Dry Dock 3, floated off, maneuvered
under the Glomar Explorer and into the aperture. Their close fit
allowed fast attachment to temporary suspension brackets in the
main hold. The ship was lifted again, this time on standard 6-foot
(1.8 m) blocking. On the dry dock, floor welders quickly began connecting
the new bottoms to the original 1.75-inch (4.4cm) plate. Only when
this stage was structurally complete could the interior construction
begin.
Two bulkheads were erected
fore and aft of the drilling well, creating new decked holds. The
fore space will carry 40,000 feet (12,192 m) of riser pipe and related
handling equipment. The aft now contains ten 40- x 15-foot (12.2
x 4.6 m) mud tanks and 4 each 7,500 psi mud pumps. The largest fitting
in the well is the 25-ton (22.7 m ton) vertical rack which guides
the blow-out preventer through the moon pool.
Integral to its new
role of deep water oil prospecting, the Glomar Explorer will have
the ability to hold position of +10 feet (+3 m) over a drill site
up to 7,500 feet (2,286 m) deep. Cascade General crews overhauled
the existing array of 2,000 HP shaft-driven thrusters - three in
the bow and two in the stern - and added four, 3,000 HP, azimuthing
units operating in 50 X 12.5-foot (15.2 x 3.8 m) vertical tubes.
These electric thrusters can be raised and inspected at deck level
via a vertical rail system - the entire installation calling for
machine-level tolerances.
The total power of the
nine thrusters, 22,000 HP, is now greater than the ship's twin-screw
propulsion system. All eleven screws will be connected to the vessel's
new dynamic-positioning system which will utilize GPS satellites
and a hydrophone system below water. The acoustic signals will be
received by six receptors which will operate in tubes projecting
below the hull. The largest thru-hull structure is a 16 X 19-foot
(4.9 x 5.8 m) moon pool designed specifically for Remote Operated
Vehicle (ROV) deployment. The ROV will have the ability to inspect
the wellhead at great depths and will have its own service facilities
and stowage area.
To meet the increased
power demands, four EMD 645 16-cylinder AC generators have been
installed forward of the old engine room. The ship's original diesel-electric
system comprising five Nordberg 16-cylinder AC generators and six
2,200 HP DC shaft motors has been re-built and activated after 16
years in layup.
"We found the ship
was well preserved," reported Cascade General's Ship Superintendent
Jim Mattix. "Our goal is to restore full operational readiness.
We are overhauling all systems -- including electrical, piping,
ventilation, shafts and steering. When she departs, the entire vessel
will be in first-class voyage condition."
When dry dock work is
complete, the ship will be berthed dockside for a second critical
maneuver. The last remnant of the Glomar Explorer's original, 17,000,000-pound
(7,711,030 kg) lifting capacity is a pair of trusses which supported
the derrick. At 150 tons (136 m tons) each, these beams are beyond
the dockside capacity of any other US West Coast repair facility
and will require the coordinated efforts of two of Cascade General's
largest Whirley cranes.
This heavy lift will
clear the way for construction of new deck levels, on-deck pipe
racks and a new drilling substructure. The pedestals for two Seatrax
cranes, with boom lengths of 90-110 feet (27.4 - 33.5 m) will then
be built over the original side decks.
Coincidentally, the
Glomar Explorer was drydocked when mothballed in Portland in 1980.
When it leaves this summer, it will be delivered under its own power
to the Gulf Coast around South America, where it will be fitted
out with the rest of its state-of-the-art drilling equipment and
commence work under a five-year, exploration contract in early 1998.
According to Jeff Shepard,
Global Marine Construction Manager, "The work accomplished
in Portland has been a critical milestone in the process of creating
a state-of-the-art, deep-water drill ship. Our company has made
a significant investment to stay on the leading edge of exploration
technology. Reflecting on the conversion work, he added, "Taking
on a conversion of this size and complexity is a challenge for any
shipyard. Cascade General has the unique features, manpower and
expertise required to perform this kind of conversion, and they
are responsive to the needs of the owners."
|
|
|
Related
articles
Cascade
General Awarded Largest Conversion Contract in History of Portland
Shipyard
Glomar Explorer
(Project Profile)
|